I am trying to set up an airflow cluster for recurrent job, for example hourly job run at the 5th mins in every hour. The job run but start time is always one hour later than its scheduled time (execution time).
dag = DAG(dag_id="dag_id",
description=d'some jobs',
schedule_interval="5 * * * *",
default_args=default_args,
start_date=datetime(2019, 7, 24), catchup=True)
Task Instance Attributes:
execution_date : 2019-08-08T16:05:00+00:00
start_date : 2019-08-08 17:05:19.007417+00:00
end_date : 2019-08-08 17:05:28.065114+00:00
The scheduler runs at the end of each period. The idea is that data for 5:05 to 6:05 cannot be processed until 6:05.
The best place I've seen this described is on a slideshow by one of the Airflow committers. See slides 11-13: https://drive.google.com/file/d/1DVN4HXtOC-HXvv00sEkoB90mxLDnCIKc/view
Related
I have two dags: The first one extracts data from one database to another. I want it to run everyday at 4 AM and then, that's how I defined my params:
Note: The code has 7am instead of 4 because Airflow is in UTC time and my time is GMT-3.
start_date=datetime(2022, 9, 6),
schedule_interval="0 7 * * *",
catchup=False
) as dag:
But, when I check Airflow's UI, the DAG time is shown like this:
screenshot
I have no idea about or have seen this Data Interval, why is it starting at today 21:00 (9 PM) and why this is the next run for this DAG?
How do I set my DAG to run at the next day (Sep 6, as I'm posting on 5) at 4 AM?
Thank you!
I have one problem, I need to launch one DAG every first day of month, but I have one problem, the DAG started on 1 October but executed that day on 1 November, I need that 1 October execute 1 October and 1 November execute 1 November, and not delay the execution one month.
My scheduler was: '0 10 1 * *'
Thanks
This is how Airflow works.
Airflow schedule DAGs at the end of the interval.
So if you have:
DAG(
dag_id='tutorial',
schedule_interval='0 10 1 * *',
start_date=datetime(2021, 10, 1),
)
The first run will start on 2021-11-01 - this run will have execution date of 2021-10-01. This behavior is consistent with how data pipelines work. In November you will want to process October data. Or in the terminology that I mentioned before - Your monthly interval starts on beginning of October it ends in November so at the beginning of November you can run the job that process October data.
That said - In the job itself you can process any interval you wish. For that you can use Airflow macros.
In simple words if you want your first DAG run to start on 2021-10-01 you should set start_date=datetime(2021, 9, 1)
Starting from Airflow 2.2.0 there was enhancement in that area.
Airflow decoupled the "When to run" from the "What interval to process" with the completion of AIP- 39 Richer Scheduler. You can read about the concept of Timetables in this doc.
I have to schedule a DAG that should run on 15th of every month. However, if 15th falls on a Sunday/Saturday then the DAG should skip weekends and run on coming Monday.
For example, May 15 2021 falls on a Saturday. So, instead of running on 15th of May, the DAG should run on 17th, which is Monday.
Can you please help to schedule it in airflow?
Thanks in advance!
The logic of scheduling is limited by what you can do with single cron expression. So if you can't say it in cron expression you can't provide such scheduling in Airflow. For that reason there is an open airflow improvement proposal AIP-39 Richer scheduler_interval to give more scheduling capabilities.
That said, you can still get the desired functionality by writing some code.
You can set your dag to start on the 15th of each month and then place a sensor that verify that the date is Mon-Fri (if not it will wait):
from airflow.sensors.weekday import DayOfWeekSensor
dag = DAG(
dag_id='work',
schedule_interval='0 0 15 * *',
default_args=default_args,
description='Schedule a Job on 15 of each month',
)
weekend_check = DayOfWeekSensor(
task_id='weekday_check_task',
week_day={'Monday', 'Tuesday', 'Wednesday', 'Thursday', 'Friday'},
mode='reschedule',
dag=dag)
op_1 = YourOperator(task_id='op1_task',dag=dag)
weekend_check >> op_1
Note: If you are running airflow<2.0.0 you will need to change the import to:
from airflow.contrib.sensors.weekday_sensor import DayOfWeekSensor
The answer posted by Elad works pretty well. I came up with another solution that works as well.
I scheduled the job to run on 15,16 and 17 of the month. However, I added a condition so that the job runs on the 15th if its a weekday. The job runs on 16th and 17th if its a Monday.
To achieve that, I added a BranchPythonOperator:
from airflow.operators.python_operator import BranchPythonOperator
def _conditinal_task_initiator(**kwargs):
execution_date=kwargs['execution_date']
if int(datetime.strftime(execution_date,'%d'))==15 and (execution_date.weekday()<5):
return 'dummy_task_run_cmo_longit'
elif int(datetime.strftime(execution_date,'%d'))==16 and (execution_date.weekday()==0):
return 'dummy_task_run_cmo_longit'
elif int(datetime.strftime(execution_date,'%d'))==17 and (execution_date.weekday()==0):
return 'dummy_task_run_cmo_longit'
else:
return 'dummy_task_skip_cmo_longit'
with DAG(dag_id='NXS_FM_LOAD_CMO_CHOICE_LONGIT',default_args = default_args, schedule_interval = "0 8 15-17 * *", catchup=False) as dag:
conditinal_task_initiator=BranchPythonOperator(
task_id='cond_task_check_day',
provide_context=True,
python_callable=_conditinal_task_initiator,
do_xcom_push=False)
dummy_task_run_cmo_longit=DummyOperator(
task_id='dummy_task_run_cmo_longit')
dummy_task_skip_cmo_longit=DummyOperator(
task_id='dummy_task_skip_cmo_longit')
conditinal_task_initiator >> [dummy_task_run_cmo_longit,dummy_task_skip_cmo_longit]
dummy_task_run_cmo_longit >> <main tasks for execution>
Using this, the job'll run on 15,16 and 17 of every month. However, it'll run the functional tasks only once every month.
In Airflow, I'd like a job to run at specific time each day in a non-UTC timezone. How can I go about scheduling this?
The problem is that once daylight savings time is triggered, my job will either be running an hour too soon or an hour too late. In the Airflow docs, it seems like this is a known issue:
In case you set a cron schedule, Airflow assumes you will always want
to run at the exact same time. It will then ignore day light savings
time. Thus, if you have a schedule that says run at end of interval
every day at 08:00 GMT+1 it will always run end of interval 08:00
GMT+1, regardless if day light savings time is in place.
Has anyone else run into this issue? Is there a work around? Surely the best practice cannot be to alter all the scheduled times after Daylight Savings Time occurs?
Thanks.
Starting with Airflow 1.10, time-zone aware DAGs can be defined using time-zone aware datetime objects to specify start_date. For Airflow to schedule DAG runs always at the same time (regardless of a possible daylight-saving-time switch), use cron expressions to specify schedule_interval. To make Airflow schedule DAG runs with fixed intervals (regardless of a possible daylight-saving-time switch), use datetime.timedelta() to specify schedule_interval.
For example, consider the following code that, first, uses a cron expression to schedule two consecutive DAG runs, and then uses a fixed interval to do the same.
import pendulum
from airflow import DAG
from datetime import datetime, timedelta
START_DATE = datetime(
year=2019,
month=10,
day=25,
hour=8,
minute=0,
tzinfo=pendulum.timezone('Europe/Kiev'),
)
def gen_execution_dates(start_date, schedule_interval):
dag = DAG(
dag_id='id', start_date=start_date, schedule_interval=schedule_interval
)
execution_date = dag.start_date
for i in range(1, 3):
execution_date = dag.following_schedule(execution_date)
print(
f'[Run {i}: Execution Date for "{schedule_interval}"]:',
dag.timezone.convert(execution_date),
)
gen_execution_dates(START_DATE, '0 8 * * *')
gen_execution_dates(START_DATE, timedelta(days=1))
Running the code produces the following output:
[Run 1: Execution Date for "0 8 * * *"]: 2019-10-26 08:00:00+03:00
[Run 2: Execution Date for "0 8 * * *"]: 2019-10-27 08:00:00+02:00
[Run 1: Execution Date for "1 day, 0:00:00"]: 2019-10-26 08:00:00+03:00
[Run 2: Execution Date for "1 day, 0:00:00"]: 2019-10-27 07:00:00+02:00
For the zone [Europe/Kiev], the daylight saving time of 2019 ends on 2019-10-27 at 03:00:00+03:00. That is, between Run 1 and Run 2 in our example.
The first two output lines show that for the DAG runs scheduled with a cron expression the first run and second run are both scheduled for 08:00 (although, in different timezones: Eastern European Summer Time (EEST) and Eastern European Time (EET) respectively).
The last two output lines show that for the DAG runs scheduled with a fixed interval the first run is scheduled for 08:00 (EEST), and the second run is scheduled exactly 1 day (24 hours) later, which is at 07:00 (EET) due to the daylight-saving-time switch.
The following figure illustrates the example:
I take input from the user about the schedule of the tasks. I want to run the task multiple times a day. How is it possible using Airflow?
You can schedule a DAG to run multiple times a day by using the schedule_interval arg in your DAG like so:
dag = DAG(
dag_id='fake_dag',
schedule_interval="* * * * *"
)
schedule_interval uses CRON format. This may help you understand CRON format.
Example: if you want your DAG to run every 4 hours during a day, your DAG would look like below:
dag = DAG(
dag_id='fake_dag',
schedule_interval="* 0-23/4 * * *"
)