In a CPU with a four (4)-stage pipeline composed of fetch, decode, execute, and write
back, each stage takes 10, 6, 8, and 8 ns, respectively. Which of the following is an
approximate average instruction execution time in nanoseconds (ns) in the CPU? Here, the
number of instructions to be executed is sufficiently large. In addition, the overhead for the
pipelining process is negligible, and the latency impact from all hazards is ignored.
a) 6
b) 8
c) 10
d) 32
Answer is 10ns.But i thought it might be 8ns since execute stage takes 8ns.please explain simply.thanks

Each instruction must go though the four stages. Once the pipeline is full, the flow of instructions in and out is determined by the duration of the longest stage:
Fetch|Decode|Exec|Write|
10ns | 6ns |8ns | 8ns |
-----+------+----+-----+
I7 I6 I5 --> I4 : I3 : I2 : I1 --> out
-----+------+----+-----+
I1..I7 are instructions. I1..I4 are in the pipeline, I5..I7 are
waiting to enter the pipeline.
After 6ns I3 is ready to move from Decode to Exec, but cannot because the stage Exec is still occupied by I2
After 2ns more (8ns total), I1 moves out of Write, I2 moves from Exec to Write, and I3 can finally move from Decode to Exec
I4 is still blocking Fetch, so I5 cannot enter
After 2ns more (10ns total) I4 moves from Fetch to Exec, and I5 can enter.
You see that the pipeline stalls until the longest stage is completed; one instruction enters the pipeline every 10ns. (The Decode stage will be idle 40% percent of the time, and the Exec and Write stages 20% of the time.)

In a pipelined situation, "the rate at which an output is produced" is determined by the slowest stage. It doesn't matter how fast the rest of the pipeline works, things are bound by the rate decoder operates. Therefore we could expect the pipeline to produce an output every 10 ns. "The rate at which an output is produced" can be interpreted as the average execution time. So its 10 ns.

Related

Effective total time for a callee function is higher than that of caller function in intel-vtune

I have a multi-threading application and when I run vtune-profiler on it, under the caller/callee tab, I see that the callee function's CPU Time: Total - Effective Time is larger than caller function's CPU Time: Total - Effective Time.
eg.
caller function - A
callee function - B (no one calls B but A)
Function
CPU time: Total
-
Effective Time
A
54%
B
57%
My understanding is that Cpu Time: Total is the sum of CPU time: self + time of all the callee's of that function. By that definition should not Cpu Time: Total of A be greater than B?
What am I missing here?
It might have happened that the function B is being called by some other function along with A so there must be this issue.
Intel VTune profiler works by sampling and numbers are less accurate for short run time. If your application runs for a very short duration you could consider using allow multiple runs in VTune or increasing the run time.
Also Intel VTune Profiler sometimes rounds off the numbers so it might not give ideal result but the difference is very small like 0.1% but in your question its 3% difference so this won't be the reason for it.

Calculate Queue Wait Times

I am looking to calculate the wait in a queue per position or a general time based on your queue position. It is a FIFO.
List of current performance status of the service
Size AvTime Queue Processing AvgFileSize(mb)
1 (0 - 1 mb) 2.57 18 3 0.21
2 (1 - 5 mb) 12.43 2 4 2.16
3 (5 - 10 mb) 23.38 9 8 6.72
4 (10 - 25 mb) 38.17 1 4 12.52
5 (>= 25 mb) 109.31 0 0 32.41
The current list of processing and queued batch files. Only lists the current users files so that is why there are queue numbers missing.
Queue Filename Status
30 Batch (3456).XML(2) Queue
20 Batch (2399).xml(3) Queue
14 batch (1495).xml(1) Queue
12 batch (1497).xml(1) Queue
15 batch (1499).xml(1) Queue
10 batch (1500).xml(4) Queue
13 batch (1496).xml(1) Queue
11 batch (1501).xml(1) Queue
9 batch (1498).xml(1) Queue
8 batch (1494).xml(1) Queue
7 batch (1493).xml(1) Queue
6 batch (1492).xml(1) Queue
5 batch (1491).xml(1) Queue
4 batch (1490).xml(1) Queue
3 batch (1).xml(1) Queue
2 Batch1.xml(1) Queue
1 Batch1.XML(2) Queue
Batch1.xml(1) Processing
Batch1.xml(1) Processing
Batch1.xml(3) Processing
Batch1.xml(4) Processing
Batch1.xml(1) Processing
Batch1.xml(3) Processing
Batch1.xml(3) Processing
Batch1.xml(3) Processing
Batch1.xml(4) Processing
Batch1.xml(4) Processing
Batch1.xml(2) Processing
Batch1.xml(3) Processing
Batch1.xml(3) Processing
Batch1.xml(2) Processing
Batch1.xml(2) Processing
Batch1.xml(3) Processing
Batch1.xml(3) Processing
Batch1.xml(4) Processing
Batch1.xml(2) Processing
So I am looking to add more information to the list how long until a batch file at position 20 will be waiting in the queue before it starts processing.
Queue Filename Status
30 (*30min) Batch (3456).XML(2) Queue
20 (*10min) Batch (2399).xml(3) Queue
...
*estimated
Your question doesn't quite provide enough context to make it possible to answer, but I can make some guesses based on the sample displays you provided.
Looks like you have a "single queue, multiple server" setup. In other words, you have a single FIFO queue, and a some fixed number N of jobs that can be in processing at any given time. Is that right?
For your algorithm, let's assume you have the following information:
Position of our job in queue (position N means there are N jobs ahead
of us)
Size of our job
Size of each job ahead of us in the queue
Pool of jobs being processed, with a certain maximum size N
Size of each job currently being processed
Elapsed time for each job currently in process (how long since that job started)
First of all, you will need a function ExpectedJobDuration(jobsize) that computes an expected job processing time for a job of a given size, based on the statistics shown in your "performance status" table. This looks pretty straightforward. Given a job size, first figure out which of your five size categories it falls into (0: 0-1mb, 1: 1-5mb, etc.) Then take your job size and multiply by the average time divided by the average size of jobs in that category. That will give you an estimate of ExpectedJobDuration(jobsize), which will tell you how long it takes to run a job of a given size, under the assumption that job time is proportional to job size, for jobs within a particular size range.
Now, for a job of a given size that's already been in process for a given time ElapsedProcessingTime, how long do we expect it to to take complete? A simple answer would be something like:
ExpectedRemainingTime = ExpectedJobDuration(jobsize) - ElapsedProcessingTime.
For jobs sitting the the queue this will be exactly the same as the expected job duration; for jobs already being processed we subtract the time the job has already been in work. However, if there is some random variation in job processing times, this is not exactly right, and could turn out to be negative. This is sort of like the actuarial problem: the average lifespan of a person is X years, how long do we expect someone to live if they are already Y years old? You would need a lot more statistical data to compute this, so for practical purposes, if the answer comes out negative, just set it to zero. (If someone is 100 years old, and the average human lifespan is 90, expect them to die at any moment. That's not quite right, but perhaps OK as a first approximation. Unless you are the 100 year old person, and not yet ready to die. :-))
OK, now we have a way to compute how long each job ahead of us in the queue should take, and how long it should take to complete jobs already in process.
If the number of jobs currently being processed is less than N (the max that can be processed at any given time) then our job can start right away. So in that case we have the answer - expected delay until our job can start is zero seconds.
Now let's look at the case where we are in position 0 in the queue. That means there are no jobs ahead of us in the queue, so our expected time to start is the minimum of the ExpectedRemainingTime of the jobs in the processing pool.
Now that gives us the basis for a recursive function that computes delay until our expected start time.
DelayUntilStart(jobPool, currentJob, queue) {
find minJob in jobPool with minimum ExpectedRemainingTIme
if currentJob is in position zero of queue
return expectedRemainingTime(minJob)
else
remove minJob from jobPool
pop the top job from the queue and put it in the jobPool
return ExpectedRemainingTime(minJob) + DelayUntilStart(jobPool, currentJob, queue)
done
}
Note - we may have a very long job ahead of us in the queue - but that doesn't mean we have to wait for it to complete. We just have to wait for it to get into the pool of jobs currently being processed, and then a shorter job might complete and let us into the pool.
The algorithm I just described is going to be an approximation. But it's probably about as good you are going to get without a lot of statistics about job processing times. For practical purposes I bet it would work pretty well.

groupsize vs execution time?

I make a simple program abput a vector adder and want to test the execution time vs the groupsize.
when I change the groupsize from 1024 to 5012 to 256 and to 128. The execution time is very similar. Why? in my view, when I `use smaller groupsizes, we should have more groups and they can work in the cores in parallel which could lead less execution time(for example, if workgroupsize change from 512 to 256, the execution time should reduce half?) but in my experinment in gpu, the execution time is siilar? is my view wrong?
Because number of workitems per group is not a visible bottleneck for vector addition. The global memory performance ise bottleneck. If data comes from host then pci-e performance is also bottleneck.

How to computer sending/receiving process in MPI_Allreduce

In MPI_Allreduce() each step you send a number of bytes to another process. You also receive a number of bytes from the same process you're sending to.
Is there an straightforward way to compute these partner processes? For example:
In step 0: process 0-1, 2-3, ...
In step 1: process 0-2, 1-3, ...
In step 2: process 0-4, ...

How does this formula that calculates CPU utilization work?

I've been given this question
Consider a system running ten I/0-bound tasks and one CpU-bound task. Assume that the I/O-bound tasks issue and I/O operation once for every millisecond of CPU computing and that each I/O operation takes 10 milliseconds to complete. Also assume that the context-switching overhead is .1 millisecond and that all processes are long running tasks Describe the CPU utilization for round-robin scheduler when:
a. The time quantum is 1 millisecond
b. The time quantum is 10 milliseconds
and I found answer for it
The time quantum is 1 millisecond: Irrespective of which process is scheduled, the
scheduler incurs a 0.1 millisecond context-switching cost for every context-switch.
This results in a CPU utilization of 1/1.1 * 100 = 91%.
The time quantum is 10 milliseconds: The I/O-bound tasks incur a context switch
after using up only 1 millisecond of the time quantum. The time required to cycle
through all the processes is therefore 10*1.1 + 10.1 (as each I/O-bound task
executes for 1millisecond and then incur the context switch task, whereas the CPU-
bound task executes for 10 milliseconds before incurring a context switch). The CPU
utilization is therefore 20/21.1 * 100 = 94%.
My only question how is this person deriving the formula for CPU Utilization? I can't seem to under stand where he/she is getting the numbers 20/21.1 * 100 = 94%, and 1/1.1 * 100 = 91%.
For the first case, every task uses 1msec to do work and .1msec to switch; thus, it is spending 1 of every 1.1 msec doing work.
For the second case, it is similar: of the 21.1 msec spent to go through all tasks, only 20 of that is doing actual work.
This is the best possible explanation to above problem :
http://jade-cheng.com/uh/coursework/ics-412/homework-4.pdf
for part a
we have 11 process(10 i/o,1 cpu). Each takes 1ms execution time and 0.1ms switching time.
So total time taken by a process is: 10(I/o)*1(1ms of cpu)+1(CPU bounded process)*1(1ms of cpu)+11*0.1(total switching time)=12.1ms.
In this 12.1ms, time for which cpu was busy/doing execution=10*1(For 10 I/O precoess)+1*1(for 1 CPU process)=10+1=11
CPU utilisation=(11/12.1)*100=(1/1.1)*100=91%approx
for part b
Though time quantum is 10ms, but I/O bound process will only occupy 1ms of cpu and then go to block state as it need I/O, and thus there is 0.1ms of context switching.
So total time taken by I/O bound process will be= 10*1
But CPU bounded process uses its whole 10ms of time slice and 0.1ms of switching. So it takes total time of 1*10=10ms
And total context switching time=11*0.1=1.1ms
Therefor total time taken=10+10+1.1=21.1ms
and time for which cpu was busy/doing execution=10*1+1*10=20
CPU utilisation=(20/21.1)*100=94%approx
I was going through the same question. this is how i understood it
In first case , when time quantum is 1 msec, if we think about gantt chart, all I/O bound process will come (lets call p1-p10) followed by p11 which is CPU bound. so total 10 context switches in 11 ms. so effective work done by CPU in that 11 msec is only 11-(10*.1ms) ie 10 ms. so CPU utilization is (10/11)*100= 90%
same way, in 2nd case, there will be 11 switches(last one is of CPU bound process) if i consider 20.1 msec of time. so effective time cpu worked is 20.1-(11*.1)= 19ms. so CPU utilization (19/20.1)*100=94%
I was confused beyond belief for some reason on this question...after looking at all the answers here I finally understood through carefully looking at the jade-cheng link given by another user. There was no formula I could find in the book (maybe I missed it) but here is my version of the answer, in a kind of pseudo-formula style:
WARNING: This is probably wrong, but maybe you can show me where I went wrong.
a)
[(10 I/O processes)(1ms) + (1 cpu process)(1ms)] / [(10 I/O processes)(1ms) + (1 cpu process)(1ms) + (10 context switches)*(0.1ms)] = 10/11 = 91%
b)
[(10 I/O processes)(1ms) + (1 cpu process)(10ms)] / [(10 I/O processes)(1ms) + (1 cpu process)(10ms) + (10 context switches)*(0.1ms)] = 20/21 = 95%