We want to use Fullcalendar [monthly] view . we want to implement a calendar with
current month as October
which starts from 10 Oct 2013 to 20th Nov 2013 {42-DAY MONTH WINDOW}
I don't find any input parameters to be provided to calendar which takes Start date[20 Oct 2013] and end date[20 Nov 2013].
Please guide me out
I'm not sure I totally get what you are trying to achieve, but you could use the
Go To date function on document.ready to jump to October.
then only allow using the calendar next button once -
(hide the previous button on start, than after clicking the next button hide it and show the previous button and vice versa).
Related
Rjs calander skip month change when I am using mouse pad and change the month it's skip month ex(I am click on March month to previous month that means Feb but it's skip Feb show January)but no issue in mouse only using laptop how to solve this issue using asp.net
I'm using the fullcalendar v4 and angular 8.
As current calendar feature, the month view always show the range of date in the month which is showing, it might have some date of previous month or next month due to 30 or 31 days for a month.
I would like to move today date to first cell of month view.
For example:
Today is 16 Dec 2020, so i would like the month view should start at 16 Dec 2020 and end at 16 Jan 2021 ( it means the 16 Dec 2020 would be at the first cell of calendar
If you are talking about Full Calendar V4, then you should set showNonCurrentDates: false. It hides previous and next month's days and also does not pass the previous/next month's dates in the events URL.
Racking my brain trying to get the TimelineYear view to start at a certain date. I have the Scheduler Plugin.
E.g.
https://fullcalendar.io/js/fullcalendar-scheduler-1.7.1/demos/scale.html
When you click on the Year button, it starts in Jan. Using Start Date, Visable Range, nothing works. Id like Todays date to be viewable automatically without having to scroll across to September as an example.
Any ideas?
Having problem for "all-day" event that an event with start Nov 10 and end Nov 12 will span only 2 days on the calendar.
Looks like the documentation for the old version has the right one that I want it to work.
But with the new version, is there a way I can make it span for 3 days instead of 2 days without changing the end date?
The problem of changing the end date is that I allow user to store the end date. I don't think changing the end date from the user input is a good idea.
Any suggestion?
Yes, it looks like it is defined in that way in full calendar. For example if you drop some event on 3rd march for 1 day then
start : Mar 03 2020 00:00:00
end : Mar 04 2020 00:00:00
Hope it helps.
I've opened an issue about (what I assume) is a bug in Google App Scripts but it doesn't look like its being monitored so I wondering if anyone has a work around for my problem.
In summary I am running a script (via a google spreadsheet) which attempts to put an entry in a Google Calendar I created.
function testCalendarAllDayEvent(){
var calendar = CalendarApp.getCalendarById("od4434jhedv936p65gcbl3bjg#group.calendar.google.com");
var calTimezone = calendar.getTimeZone();
var scriptTimezone = Session.getTimeZone();
var calendarevent = calendar.createAllDayEvent("Test Event", new Date(2011,7,1));
var summary = calendarevent.getStartTime();
}
So the above code adds the "Test Event" on the 31st July 2011 instead of the 1st July. If I change it to
new Date (2011,7,2)it puts it in on the 1st August 2011. So it seems to be 30 days out.
The reason I look at the time zones it to ensure they are the same. When I look at the summary variable value it is Mon Aug 01 2011 01:00:00 GMT+0100 (IST)
I don't want to blindly add 30 days to all dates as it will just end in tears. Does anyone know if what I am doing is incorrect? I've used Google examples as templates.
The issue here is that the Date constructor takes a zero-based month index. So
new Date(2011,7,1) creates a Date of Aug 1 2011.
whereas
new Date(2011,6,1) creates a Date of July 1 2011.