I'm trying to have a single (if possible) event or multiple events linked to each other with multiple dates and hours. So that the user can have a delete all option related to this event(s).
Original hours in postman body:
"start": {
"dateTime": "2022-09-01T09:00:00+02:00",
"timeZone": "Europe/Brussels"
},
"end": {
"dateTime": "2022-09-01T17:00:00+02:00",
"timeZone": "Europe/Brussels"
},
"Recurring" hours:
2022 09 02 10:00:00 → 2022 09 02 15:00:00
2022 09 03 10:00:00 → 2022 09 03 19:00:00
I tried to use the recurrence with RDATE;VALUE=DATE:20220902T100000/20220902T150000,20220903T100000/20220903T190000, tried to use some combination of UNTILL and the previous value but this will always take the original hours.
Then I found the related-to documentation but I'm unable to link the first event to the rest as the documentation uses an email and not an id which is what I would expect.
The following is an example of this property:
RELATED-TO:jsmith.part7.19960817T083000.xyzMail#example.com
RELATED-TO:19960401-080045-4000F192713-0052#example.com
Is there a way to have a single event with multiple dates and multiple hours or are multiple events the only way?
How would I begin "linking" them together so the user can have the delete all option?

Related

How can I change a UTC moment.js object to reflect the "zone" property it already has?

Ok so I have this moment object I'm looking at in Developer Tools:
amoment: Moment
_a: (7) [2017, 4, 21, 20, 15, 0, 0]
_d: Sun May 21 2017 15:15:00 GMT-0500 (Central Daylight Time) {}
_f: "MM/DD/YYYY h:mm A"
_i: "5/21/2017 8:15:00 PM"
_isAMomentObject: true
_isUTC: true
_isValid: true
_locale: Locale {_calendar: {…}, _longDateFormat: {…}, _invalidDate: "Invalid date", ordinal: ƒ, _dayOfMonthOrdinalParse: /\d{1,2}(th|st|nd|rd)/, …}
_offset: -180
_pf: {empty: false, unusedTokens: Array(0), unusedInput: Array(1), overflow: -1, charsLeftOver: 3, …}
_strict: false
_z: Zone {name: "America/Halifax", abbrs: Array(229), untils: Array(229), offsets: Array(229), population: 390000}
__proto__: Object
As you can see, the text representation is 5/21/2017 8:15:00 pm. This is the correct time in UTC and I notice "_isUTC" is "true".
The _d property shows that datetime in CDT, where I am now.
The _z property shows a Zone object set to "America/Halifax"--this is dynamically set elsewhere, but also correct.
I would like to return a moment reading "5/21/2017 5:15:00 pm" because that's what that datetime is in "America/Halifax."
There are so many moment.js functions I haven't found the right way to do this.
All of the fields that begin with underscores (_) are meant to be internal to Moment. You should not be using them at all. More on this here, and here.
To output a string in a particular format from a moment object, use the format function. For example:
yourMomentObject.format("M/D/YYYY h:mm:ss a") //=> "5/21/2017 5:17:00 pm"
I ended up doing new Date(amoment.format('YYYY-MM-DDTHH:mm:ss+00:00')); which worked for my purposes. The zone kept wanting to render the date in that zone, so I just had to omit it.

Email time format to logstash #timestamp

I'm trying to parse email date field to Logstash #timestamp field:
Example email date filed: Mon, 28 May 2018 15:53:54 +0100
Logstash config: filter {date {match => ["date", "E, d MMMM yyyy HH:mm:ss Z"]}
Result #timestamp: May 28th 2018, 14:53:54 +0000
As you can see Logstash haven't added +0100.
Could you please tell me where I have done wrong?

.NET thread vanished

I have dump of w3wp process (taken by procdump) where I see strange situation.
Simplified version on my code:
logger.Log(Thread.CurrentThread.ManagedThreadId);
using(semaphore_release_on_dispose_object)
{
// some third party code with unmanaged parts
DangerousCode();
}
semaphore_release_on_dispose_object - release semaphore in Dispose.
Process dump was taken after some timeout, when it was clear that semaphore was not released
I found thread in dump, but it seems become 'bad'. It listed by ~ command, but not listed by !threads command. When I switch to it I can see unmanaged stack, but not managed:
0:004> ~
...
3 Id: 63ec.11b0 Suspend: 1 Teb: 000007ff`fffae000 Unfrozen
...
0:004> ~~[11b0]s
ntdll!NtRemoveIoCompletion+0xa:
00000000`76e913aa c3 ret
0:003> k
# Child-SP RetAddr Call Site
00 00000000`01a3f818 000007fe`fcea169d ntdll!NtRemoveIoCompletion+0xa
01 00000000`01a3f820 00000000`76d2a4e1 KERNELBASE!GetQueuedCompletionStatus+0x39
02 00000000`01a3f880 000007fe`f0311f7b kernel32!GetQueuedCompletionStatusStub+0x11
03 00000000`01a3f8c0 000007fe`f0312024 w3tp!THREAD_POOL_DATA::ThreadPoolThread+0x3b
04 00000000`01a3f910 000007fe`f03120a1 w3tp!THREAD_POOL_DATA::ThreadPoolThread+0x34
05 00000000`01a3f940 00000000`76d3652d w3tp!THREAD_MANAGER::ThreadManagerThread+0x61
06 00000000`01a3f970 00000000`76e6c521 kernel32!BaseThreadInitThunk+0xd
07 00000000`01a3f9a0 00000000`00000000 ntdll!RtlUserThreadStart+0x1d
0:003> !clrstack
OS Thread Id: 0x11b0 (3)
Child SP IP Call Site
GetFrameContext failed: 1
0000000000000000 0000000000000000
So, I assume that somehow third party code some how 'broke' thread and skip finally block (using).
Any ideas how it is possible?

PSI - Statusing Web Service - Results not as expected

I'm trying to update Status information on assignments via Statusing Web Service (PSI). Problem is, that the results are not as expected. I'll try to explain what I'm doing in detail:
Two cases:
1) An assignment for the resource exists on specified tasks. I want to report work actuals (update status).
2) There is no assignment for the resource on specified tasks. I want to create the assignment and report work actuals.
I have one task in my project (Auto scheduled, Fixed work). Resource availability of all resources is set to 100%. They all have the same calendar.
Name: Task 31 - Fixed Work
Duration: 12,5 days?
Start: Thu 14.03.13
Finish: Tue 02.04.13
Resource Names: Resource 1
Work: 100 hrs
First I execute an UpdateStatus with the following ChangeXML
<Changes xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema">
<Proj ID="a8a601ce-f3ab-4c01-97ce-fecdad2359d9">
<Assn ID="d7273a28-c038-486b-b997-cdb2450ceef5" ResID="8a164257-7960-4b76-9506-ccd0efabdb72">
<Change PID="251658250">900000</Change>
</Assn>
</Proj>
</Changes>
Then I call a SubmitStatusForResource
client.SubmitStatusForResource(new Guid("8a164257-7960-4b76-9506-ccd0efabdb72"), null, "auto submit PSIStatusingGateway");
The following entry pops up in approval center (which is as I expected it):
Status Update; Task 31; Task update; Resource 1; 3/20/2012; 15h; 15%;
85h
Update in Project (still looks fine):
Task Name: Task 31 - Fixed Work
Duration: 12,5 days?
Start: Thu 14.03.13
Finish: Tue 02.04.13
Resource Names: Resource 1
Work: 100 hrs
Actual Work: 15 hrs
Remaining Work: 85 hrs
Then second case is executed: First I create a new assignment...
client.CreateNewAssignmentWithWork(
sName: Task 31 - Fixed Work,
projGuid: "a8a601ce-f3ab-4c01-97ce-fecdad2359d9",
taskGuid: "024d7b61-858b-40bb-ade3-009d7d821b3f",
assnGuid: "e3451938-36a5-4df3-87b1-0eb4b25a1dab",
sumTaskGuid: Guid.Empty,
dtStart: 14.03.2013 08:00:00,
dtFinish: 02.04.2013 15:36:00,
actWork: 900000,
fMilestone: false,
fAddToTimesheet: false,
fSubmit: false,
sComment: "auto commit...");
Then I call the UpdateStatus again:
<Changes xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema">
<Proj ID="a8a601ce-f3ab-4c01-97ce-fecdad2359d9">
<Assn ID="e3451938-36a5-4df3-87b1-0eb4b25a1dab" ResID="c59ad8e2-7533-47bd-baa5-f5b03c3c43d6">
<Change PID="251658250">900000</Change>
</Assn>
</Proj>
</Changes>
And finally the SubmitStatusForResource again
client.SubmitStatusForResource(new Guid("c59ad8e2-7533-47bd-baa5-f5b03c3c43d6"), null, "auto submit PSIStatusingGateway");
This creates the following entry in approval center:
Status Update; Task 31 - Fixed Work; New reassignment request;
Resource 2; 3/20/2012; 15h; 100%; 0h
I accept it and update my project:
Name: Task 31 - Fixed Work
Duration: 6,76 days?
Start: Thu 14.03.13
Finish: Mon 25.03.13
Resource Names: Resource 1;Resource 2
Work: 69,05 hrs
Actual Work: 30 hrs
Remaining Work: 39,05 hrs
And I really don't get, why the new work would be 69,05 hours. The results I expected would have been:
Name: Task 31 - Fixed Work
Duration: 6,76 days?
Start: Thu 14.03.13
Finish: Mon 25.03.13
Resource Names: Resource 1;Resource 2
Work: 65 hrs
Actual Work: 30 hrs
Remaining Work: 35 hrs
I've spend quite a bunch of time, trying to find out, how to update the values to get the results that I want. I really would appreciate some help. This makes me want to rip my hair out!
Thanks in advance
PS: Forgot to say that I'm working with MS Project Server 2010 and MS Project Professional 2010

X Axis on Full Calendar Time settings for week and day

Could someone help me please I am not a developer/coder but am trying to use this calendar to display time intervals of 15 minutes rather than the current 30 minutes time intervals on the X axis of the display in the left hand column.
The events being booked are still 30 minutes long but start at 15 minute intervals, ie
8:00 pm - 8:30 pm
8:15 pm - 8:45 pm
8:30 pm - 9:00 pm
8:45 pm - 9:15 pm
I see the following code
//Determines the time-text that will be displayed on each event.
timeFormat:{ //Settings: http://arshaw.com/fullcalendar/docs/text/timeFormat/
// for agendaWeek and agendaDay
agenda: 'h:mm{ - h:mm}', // 5:00 - 6:30
// for all other views
'': 'h(:mm)t' // 7p
},
but dont know what to do, can you help please bearing in mind i know very little about this or should I alter the java script?
in fullcalendar.js change ....
setDefaults({
allDaySlot: true,
allDayText: 'all-day',
firstHour: 6,
slotMinutes: 15, // <<< this
defaultEventMinutes: 120,
axisFormat: 'h(:mm)tt',
timeFormat: {
agenda: 'h:mm{ - h:mm}'
},
dragOpacity: {
agenda: .5
},
minTime: 0,
maxTime: 24
});

Resources